Alltel Arena project hits another roadblock.Greenbrier greenbrier: see smilax. Contractor Given Notice of Default Nabholz building and Management Corp. of Greenbrier, a concrete contractor working on the Alltel Arena Alltel Arena is an 18,000-seat multi-purpose arena in North Little Rock, Arkansas, directly across the Arkansas River from downtown Little Rock. The arena opened in October 1999. project in North Little Rock, recently hired Little Rock lawyer Cyril Hollingsworth to represent the company. It has proven to be a wise decision for Ray Nabholz, an owner of NBMC NBMC National Black Media Coalition NBMC New Brunswick Multicultural Council, Inc. (Canada) NBMC Newz Blast Media Co. NBMC Negative-Binomial Monte Carlo NBMC NORAD Battle Management Center NBMC North Belfast Musicians Collective . Last Thursday, the Multipurpose mul·ti·pur·pose adj. Designed or used for several purposes: a multipurpose room; multipurpose software. multipurpose Adjective Civic Center Facilities Board for Pulaski County Pulaski County is the name of several counties in the United States:
Should NBMC, which is not affiliated with Conway contractor Nabholz Construction Corp., be held in default, apparently Baker Concrete Construction Inc. of Monroe, Ohio Monroe is a city located in east central Butler and west central Warren counties in the southwestern part of the U.S. state of Ohio. As of the 2000 census, the city population was 7,133, up from 4,008 in 1990. , would take over the concrete work. Baker, which has assisted NBMC as a subcontractor One who takes a portion of a contract from the principal contractor or from another subcontractor. When an individual or a company is involved in a large-scale project, a contractor is often hired to see that the work is done. , never has put in a bid on the $72.3 million public project that is funded in part by more than $50 million in taxpayers' money. The actual motion before the board did not mention it, but Art Hunkele, senior project manager for VCC/Turner, said Thursday if NBMC cured the concrete within 72 hours, it could "be back to business as usual." Hours after the board meeting, no one representing NBMC would comment on the notice of default. Hollingsworth, a partner with Horne Hollingsworth & Parker in Little Rock, had not seen the notice and declined to comment Thursday. According to according to prep. 1. As stated or indicated by; on the authority of: according to historians. 2. In keeping with: according to instructions. 3. public documents, the project may be as much as four months behind schedule. An early schedule apparently indicated that steel could have been delivered as quickly as April (see a chronology chronology, n the arrangement of events in a time sequence, usually from the beginning to the end of an event. of the project on Page 22.) First steel did not go up on the job until Aug. 18, four months later. Hunkele said in a June 16 letter that the delays are the "direct result of continual slippage Slippage The difference between estimated transaction costs and the amount actually paid. Notes: Slippage is usually attributed to a change in the spread. See also: Spread, Transaction Costs Slippage of the concrete schedule." VCC/Turner is demanding that NBMC pay all extra expenses to get the project on schedule. Nabholz repeatedly has declined to discuss the situation with the media, citing a vague reference in all the contractors' contracts that "no publicity releases will be issued without prior written approval of VCC/Turner's project manager." Unbelievably, even though VCC/Turner and members of the Alltel Arena Board have known for months that the concrete schedule has been behind, no one ever chose to bring the problems before the board in open, public meetings. The biggest problem for the Alltel Arena Board and VCC/Turner may be a backlash from the publicity of the troubles with the project. There are still portions of the job that have not been bid. "[The arena board and] the county doesn't want to have a reputation for going to court," one construction management expert says. "The way they handle Nabholz could hurt them with these other packages that haven't been bid yet. If I was a contractor looking at it, I'd not want to get into that. That means the competition [for the bids] could be going down and the price [on the bids] could go up." Should the problems lead to a lawsuit by Nabholz, some experts believe Nabholz has a good chance of winning. It could take up to four years to finally win, however, possibly too late to keep NBMC solvent. NBMC or its bonding company, Mid-Continent Group of Tulsa, Okla., could be forced to pay $1 million or more, an estimate Hunkele has used, to get the job back on track. When Nabholz placed his winning bid of $4.78 million for the cast-in-place concrete work, he noted that he would take 547 days to finish the job. The arena board approved that bid and apparently never questioned NBMC's time frame. It did not correspond with VCC/Turner's schedule of a year for the work, and the construction management team quickly let NBMC know that. "From the damn first week, they just started kicking his * * * around and he's a very conciliatory con·cil·i·ate v. con·cil·i·at·ed, con·cil·i·at·ing, con·cil·i·ates v.tr. 1. To overcome the distrust or animosity of; appease. 2. young man," says one of Nabholz's friends who is knowledgeable in construction. "Writing real terrible threatening letters (Law) letters containing threats, especially those designed to extort money, or to obtain other property, by menaces; blackmailing letters. See also: Threatening , and they started calling the bonding company, trying to put doubt in [the bonding company's] mind. Look at [Hunkele's] letters, which are totally obnoxious; he's going to wish he didn't write those. You can see what kind of attitude he has." The friend says Gus Vratsinas, owner of Vratsinas Construction, and Bob Russell, chairman of the Alltel Arena Board, have been "gentlemanly" throughout NBMC's troubles. "I'm sure Vratsinas is embarrassed," the friend says. "They've got to live and work in this state. "Where Ray made his big mistake was he kept trying to take care of them as a client. They kept kicking him around. Finally he got full of it and started playing a little hard ball with them. He should have done it a long time ago. "There are two sides to every coin. I think Ray got hold of a bad job, too, underestimating what it was going to take to get it done." A construction management expert who has reviewed some of the Alltel Arena documents says, "If the contract says it's 547 days, that's what the contract says." "Any arbitrator arbitrator n. one who conducts an arbitration, and serves as a judge who conducts a "mini-trial," somewhat less formally than a court trial. In most cases the arbitraror is an attorney, either alone or as part of a panel. or judge or jury will say that's what the contract says," he says. "That's the way he bid it, so [the Alltel Arena Board] had to sign him up that way. Now they're probably trying to shrink the schedule." NBMC's problems working with VCC/Turner apparently aren't unique. Other contractors agree that working with the construction management team is difficult. Some say their payments are well past due. In May, Leon Ross of IHP ihp or i.hp. abbr. indicated horsepower Industrial Inc. of North Little Rock wrote to Paul Simonetta, senior project engineer with VCC/Turner, about delays in the project. "IHP is reaching a very critical juncture junc·ture n. The point, line, or surface of union of two parts. ," Ross wrote. "Your failure to perform is bringing unplanned cost to us." Nabholz's construction friend, who asked not to be identified, says, "Ray is just Mr. Nice Guy, but he was in there with a black widow black widow, poisonous spider of the genus Latrodectus, found throughout North and South America and common in the SW United States. The name derives from the fact that the female, like those of many other spider species, may eat the male after mating. . And they just ate his lunch." * Convention Center expansion hasn't been without its problems. * Motels Motels may refer to any of the following:
* Work on highways throughout the state is moving along, but probably not as quickly as the state's drivers want. Alltel Arena Construction Chronology Here is an abbreviated chronology on construction at the Alltel Arena with particular emphasis on the cast-in-place concrete work done by Nabholz Building and Management Co. of Greenbrier. Oct. 14, 1997: NBMC bids $4.78 million to do cast-in-place concrete work for Alltel Arena. Mobley Contractors Inc., the only other bidder on the job, bids $9.88 million. VCC/Turner's prior estimated amount for the job is $4.806 million. In his bid, Ray Nabholz, owner of NBMC, stipulates that his work will be done 547 days from his notice to proceed. Oct. 17, 1997: NBMC is given notice to proceed. 547 days later would be April 19, 1999. Dec. 3, 1997: NBMC signs a standard change order with VCC/Turner. The change indicates that NBMC "will make every good faith effort to achieve the anticipated construction schedule" but doesn't seem to indicate anything about what the schedule is. There is also no mention or disagreement with NBMC's 547-day schedule. Jan. 8, 1998: At weekly contractors meeting, NBMC is warned that "area 6 columns & tie beams must start!" (emphasis in original document). Jan. 15, 1998: At contractors meeting, Rankin Construction Co. of North Little Rock is asked to "clean reinforcing material and spoils off island. This staging area staging area n. A place where troops or equipment in transit are assembled and processed, as before a military operation. Noun 1. belongs to Nabholz, second request!" Notes of the meeting also indicate that Rankin's "manpower was 18 on [Jan. 12 and 13] and 21 on [Jan. 14]. This must improve to complete your work ahead of Nabholz." NBMC is told "rebar re·bar n. 1. A rod or bar used for reinforcement in concrete or asphalt pourings. 2. A group of such rods forming a grid. [re(inforcing) bar.] manpower must increase. Should have wall steel ready to set following forms being set." Feb. 5, 1998: At regular Alltel Arena Board meeting, Art Hunkele, senior project manager for the construction management team VCC/Turner, says that "the concrete pour of today [Feb. 5] is the first vertical pour, which means concrete columns will be appearing. AFCO AFCO Automatic Fuel Cutoff AFCO Armed Forces Career Office AFCO Air Force Cryptologic Office AFCO Australian Federation of Consumers Organisations AFCO Air Fuel Cutoff AFCO Automotive Fluid Connectors Operations AFCO Aggies for Christ in the Orient is fabricating material that will be ready in March and April." March 5, 1998: Notes of contractors meeting indicate that "[construction manager] is still holding steel delivery date [by AFCO Steel] due to Nabholz." March 12, 1998: In response to a question at contractors meeting, Tommy Doolin of VCC/Turner says that "concrete is a full two months behind schedule." Hunkele says that a recovery plan is formulated and that is to not allow the concourse schedule from sliding anymore. March 19, 1998: Weekly contractors meeting indicates "AFCO will mobilize mo·bi·lize v. 1. To make mobile or capable of movement. 2. To restore the power of motion to a joint. 3. To release into the body, as glycogen from the liver. May 1, 1998. Steel will arrive May 11, 1998." April 2, 1998: NBMC is told at contractors meeting "concrete schedule is critical. Structural steel will be on site in 46 calendar days (May 18, 1998)." Rankin Construction Co. indicates "tunnel excavation continues to be on hold, waiting on Nabholz." April 6, 1998: Ray Nabholz writes to Hunkele, "We have never agreed to change our 547 days that is on our bid form. ... Your anticipated construction schedule was inaccurate from the very first item. The bid date was scheduled to be Sept. 25, 1997, but the actual bid date was Oct. 14, 1997. The pile caps a beam resting upon and connecting the heads of piles. See also: Pile were scheduled to be complete Nov. 26, 1997, but were not complete three months later in February. ... We moved on site in December 1997 to start the walls. The site was not ready, compaction of the areas disturbed by the pile cap contractor were nonexistent non·ex·is·tence n. 1. The condition of not existing. 2. Something that does not exist. non , our equipment and personnel could not move properly on site and the pile cap contractor was not ahead of us far enough. ... We have been on site 100 days and [25 1/2 days] were lost to weather." April 16, 1998: Hunkele writes to Ray Nabholz: "We are getting the impression that you are distancing yourself from the project team. We base this on: being 'stood up' at an April 3 meeting with no phone call or response to our phone calls; limited participation at the formal partnering session on March 20 and 21; several unreturned phone calls; 'Lone Ranger' attitude displayed in your April 6 letter." April 23, 1998: At regular Alltel Arena Board meeting, Paul. Simonetta of VCC/Turner tells the board that "the project is on schedule. All contractors are proceeding in a timely fashion." May 14, 1998: Leon Ross, project manager for heating and air conditioning air conditioning, mechanical process for controlling the humidity, temperature, cleanliness, and circulation of air in buildings and rooms. Indoor air is conditioned and regulated to maintain the temperature-humidity ratio that is most comfortable and healthful. contractor IHP Industrial Inc. of North Little Rock, writes to VCC/Turner's Paul Simonetta: IHP is reaching a very critical juncture. ... IHP was to have HVAC (Heating Ventilation Air Conditioning) In the home or small office with a handful of computers, HVAC is more for human comfort than the machines. In large datacenters, a humidity-free room with a steady, cool temperature is essential for the trouble-free equipment on site as of June 8, 1998. We will have the majority of this on site by this date. ... [But] we cannot install HVAC equipment and piping without a building and you have not provided a building. Your failure to perform is bringing unplanned cost to us." June 16, 1998: Hunkele writes to Ray Nabholz (with a copy to Bob Russell, among others): "During the last three months we have met with you and/or your staff to attempt to salvage acceptable milestone dates in order to coordinate with the other trade contractors and preserve the board's schedule to complete the project by Aug. 11, 1999. The attached summary of schedules presented by your team indicates how futile this effort has been. ... Lacking confidence in your projected schedule, we extrapolated the completion date based on your average weekly concrete placement. based on a placement of 86 yards per week, NBMC will not allow the east precast/high roof to start until January 1999. ... Overall project completion would be Nov. 15, 1999, three months beyond the acceptable date, the direct result of continual slippage of the concrete schedule." June 19, 1998: Hunkele writes to Ed Moffitt of NBMC: "You have not given us your latest projection as to when you feel NBMC will be out of AFCO/Steel City's way wherein where·in adv. In what way; how: Wherein have we sinned? conj. 1. In which location; where: the country wherein those people live. 2. they can effectively start their work. We have met several times during the past two weeks with you and AFCO/Steel City to help you determine this date and you continue to be evasive e·va·sive adj. 1. Inclined or intended to evade: took evasive action. 2. Intentionally vague or ambiguous; equivocal: an evasive statement. . Previously you have committed to May 15, June 1, July 1 and now nothing! ... Please be advised that all AFCO/Steel City overhead costs overhead costs see fixed costs. incurred since June 1, 1998, will be forwarded to your account per Article 3.3.5 of the supplementary general conditions." June 22, 1998: At a concrete-in-place concrete schedule meeting attended by 11 people, including Russell, the board chairman, Hunkele says that, based on the current pace in placing concrete, NBMC's projected finish date is Sept. 20, 1999, 40 days after the planned completion of the entire arena. Nabholz says he has until April 15 to complete his work. Hunkele says delay costs incurred by other contractors will be the responsibility of NBMC. June 23, 1998: A memo from Tommy Doolin of VCC/Turner to Tim Rowlett of NBMC indicates that steel City, the contractor scheduled to install steel, has found "anchor bolts An anchor bolt is used to attach objects or structures to concrete. There are many types of anchor bolts, consisting of designs that are mostly proprietary to the manufacturing companies. All consist of a threaded end, to which a nut and washer can be attached for the external load. installed by [NBMC] that have so much concrete on them they cannot get a thread chaser to start." June 24, 1998: Hunkele writes to Ray Nabholz: "We are suspending all future premium time reimbursements for your Saturday work. We do expect you to work, at your own expense, whatever days and hours it takes to comply with the June 5, 1998, project schedule." June 25, 1998: Hunkele writes to Nabholz: "Your performance to date has prevented 200 other tradesmen from going to work. ... Ray, you need to 'jump start' the raker rake 1 n. 1. A long-handled implement with a row of projecting teeth at its head, used especially to gather leaves or to loosen or smooth earth. 2. A device that resembles such an implement. v. beams installation as well as the rest of your operation because the project can't accept continuation of the-current level of performance." June 25, 1998: Hunkele writes to Paul LaForge of Mid-Continent Group, the bonding company for NBMC: "We are very disappointed in your demeanor The outward physical behavior and appearance of a person. Demeanor is not merely what someone says but the manner in which it is said. Factors that contribute to an individual's demeanor include tone of voice, facial expressions, gestures, and carriage. and lack of positive response to our presentation [on June 22] of your client's failure to prosecute the work according to his contractual requirements. ... Failure to complete the upper raker beams by Sept. 14, 1998, as detailed in NBMC's May 20, 1998, schedule, could lead to a notice of default and financial damages assessed accordingly." July 1, 1998: James Edwards, president of Central Industrial Electrical Co., the electrical contractor, writes to Hunkele: "We are laying people off because we are so far behind and cannot keep people on the payroll waiting on the job to start." July 8, 1998: At a cast-in-place concrete meeting, Hunkele says that Alltel Arena would not be completed until Oct 22, 1999, if the current pace of concrete work continues. Hunkele indicates that Baker Concrete of Houston has been contacted about assisting NBMC. The cost would be about $500,000. Nabholz says he's facing a no-win situation Noun 1. no-win situation - a situation in which a favorable outcome is impossible; you are bound to lose whatever you do situation - a complex or critical or unusual difficulty; "the dangerous situation developed suddenly"; "that's quite a situation"; "no human . His June payment has been held up. Without progress payments, he's cash starved starve v. starved, starv·ing, starves v.intr. 1. To suffer or die from extreme or prolonged lack of food. 2. Informal To be hungry. 3. To suffer from deprivation. and out of business. If he pays $500,000 [to Baker Concrete] and another $1 million in damages and claims from other contractors and the Arena Board, he's out of business. Given these options, he'd be better off to shut down the operation and take the matter to court. He felt he'd have an excellent chance of a favorable fa·vor·a·ble adj. 1. Advantageous; helpful: favorable winds. 2. Encouraging; propitious: a favorable diagnosis. 3. settlement. Nabholz says the foundation contractor, Rankin Construction Co., was four months late and soil conditions were not in accordance with contract documents. Hunkele responds that Rankin held up Nabholz in one instance, but it was rectified rectified refined; made straight. in two weeks. July 10, 1998: Hunkele writes Nabholz that the June progress payment, which had been withheld from Nabholz, will be paid. July 15, 1998: At the regular Alltel Arena Board meeting, Paul Simonetta of VCC/Turner recommends that the board increase the overall project budget to $72.3 million, an increase of $1.3 million over the original budget of $71 million. The board unanimously accepts the recommendation. Aug. 18, 1998: First steel beams go up, 4 1/2 months after Hunkele initially indicated at Feb. 5 arena board meeting that AFCO's steel would be ready and 99 days after the May 11 arrival date for steel is mentioned in March 19 weekly contractors meeting. Aug. 20, 1998: First mention made at Alltel Arena Board meeting of any concrete delays. Project is 356 days from scheduled completion on Aug. 11, 1999. Source: Documents on file with the Alltel Arena Board. RELATED ARTICLE: If Needed, Arena Work Could Continue Until First Event If Alltel Arena isn't finished by its scheduled completion date of Aug. 11, 1999, the impact on events at the North Little Rock facility may not be significant. One executive with a national construction company says it's not unusual for a general contractor A general contractor is an organization or individual that contracts with another organization or individual (the owner) for the construction of a building, road or any other execution of work or facility. to turn a project over the night of the first event. "I've been to the point of getting food service accepted at 4 p.m. for a 7 p.m. game," says Ted Wellmeyer, an executive with Huber Hunt Nichols of Indianapolis. "If it has to go down to the wire, it goes down to the wire." The first scheduled event at Alltel Arena won't be until October 1999, when a minor league hockey team probably will play its first home game. The original plans called for Leisure Management International Inc., which will manage the arena when it opens, to have six-to-eight weeks to become familiar with the facility. "LMI LMI Labor Market Information LMI Local Management Interface LMI Logistics Management Institute LMI Linear Matrix Inequality LMI Legemiddelindustriforeningen (Norway) LMI Low to Moderate Income LMI Lender's Mortgage Insurance says the arena does not have to be 100 percent complete for them to start moving some stuff in," says Bob Russell, chairman of the Alltel Arena Board. "They say it's not going to take them two months to do their walk-through and check out all their equipment. You might even have some events in there when things that the people won't see are not completely finished." Huber Hunt Nichols built Bud Walton Arena
"You kind of dragged the broom broom, common name for plants of two closely related and similar Old World genera, Cytisus and Genista, of the family Leguminosae (pulse family). out the door as people walked in," Wellmeyer says. - David Smith |
|
||||||||||||||||||

Printer friendly
Cite/link
Email
Feedback
Reader Opinion