All systems go: Florida contractors put a UHD machine to work on a demo project at the Kennedy Space Center.


[ILLUSTRATION OMITTED]

Sunrise Systems of Brevard Inc., Cocoa, Fla., was selected to perform demolition of multiple structures at Kennedy Space Center Kennedy Space Center (Cape Canaveral) U.S.

launch site for manned space missions. [U.S. Hist.: WB, So:562]

See : Astronautics
 and Cape Canaveral Air Force Station The Cape Canaveral Air Force Station (CCAFS) is the East Coast space launch facility of the United States Department of Defense. Located on Cape Canaveral in the State of Florida, it depends on Patrick Air Force Base, home of the 45th Space Wing. CCAFS is adjacent to the John F. , through a Request for Technical Proposal early this year. This RFP (Request For Proposal) A document that invites a vendor to submit a bid for hardware, software and/or services. It may provide a general or very detailed specification of the system.

1. (business) RFP - Request for Proposal.
2.
 presented multiple environmental challenges that could best be addressed by an environmental contractor. Having partnered with Pete Charamut of Frank-Lin Excavating, Melbourne, Fla., on many projects through the years, we knew that they were more than qualified to perform all of the structural demolition required by the RFP. In fact. Frank-Lin would perform 65 percent on this particular project.

THE DIRTY WORK

SAEF SAEF South African Excellence Foundation
SAEF Spacecraft Assembly and Encapsulation Facility (NASA)
SAEF Simple Average Ensemble Forecast
SAEF St.
 II is a facility used for assembling, fueling and encapsulating satellites prior to mounting them on various types of rockets. The primary structure is an 85-foot open high bay supported with 18-inch by 33.5-inch by 1.25-inch thick wide-flange structural beams, clad in two layers of insulated aluminum siding. Two attached ancillary structures are constructed of concrete columns with poured block infill, on either side of a two-story explosion-proof control center. This facility contained asbestos materials, PCB PCB: see polychlorinated biphenyl.
PCB
 in full polychlorinated biphenyl

Any of a class of highly stable organic compounds prepared by the reaction of chlorine with biphenyl, a two-ring compound.
 containing oils, lead-based paint and PCB containing paint. Prior to demolition, all of these materials had to be properly abated and disposed of. Sunrise Systems of Brevard performed all of the abatement operations and, as prime contractor, all project oversight.

AIMING HIGH

Pete Charamut, Frank-Lin president, decided to use a high-reach shear to perform dismantling operations on the high bay structure. Kuhn Equipment of Summerville, S.C., provided a ZX460 excavator ex·ca·va·tor
n.
An instrument, such as a sharp spoon or curette, used in scraping out pathological tissue.


excavator (eks´k
 outfitted with a high reach boom and stick from Jewell Attachments, Portland, Ore., equipped with a Genesis shear. This machine would reach 90 feet and could cut through all of the support members holding the primary structure together. Using the shear in concert with loaders and Caterpillar 320 and 321 track-mounted excavators equipped with demolition thumbs and grapples, Frank-Lin methodically dismantled the structure. As debris and metals hit the ground, they were separated, metals were segregated and graded and they were loaded out. One of the challenges faced at SAEF II was protecting the roadway that ran along the west and north sides of the structure.

To avoid destroying the asphalt with the ground pressure created by a 105,000-pound machine, we placed between 24 inches and 36 inches of friable friable /fri·a·ble/ (fri´ah-b'l) easily pulverized or crumbled.

fri·a·ble
adj.
1. Readily crumbled; brittle.

2. Relating to a dry, brittle growth of bacteria.
 soil over the [sloped] roadway. This also provided us the benefit of governing the slope on the west side, leveling the surface for the shear.

[ILLUSTRATION OMITTED]

With the shell removed, and ancillary structures demolished and loaded out, we had to drop the high bay structural components in a controlled fall. Our goal was to drop all of the steel within the footprint of the building, allowing us to process the steel on a concrete surface. This approach also minimized the danger of fire while torch cutting.

There were four 3-inch threaded rods holding each structural column at the footer In a document or report, common text that appears at the bottom of every page. It usually contains the page number. . These were torched off at the base plate, and the column sets were pulled over with a steel cable and bulldozer. Once on the ground, liquid oxygen and acetylene acetylene (əsĕt`əlēn') or ethyne (ĕth`īn), HC≡CH, a colorless gas. It melts at −80.8°C; and boils at −84.0°C;.  lances were used to cut the beams into manageable pieces for transport. It was our original intent to sell these beams for re-use, but they were custom sized, mid could not be successfully marketed in the time frame allotted al·lot  
tr.v. al·lot·ted, al·lot·ting, al·lots
1. To parcel out; distribute or apportion: allotting land to homesteaders; allot blame.

2.
.

The most difficult part of this demo was the explosion-proof section of the ancillary structure. This part of the facility was constructed to withstand exploding hypergolic fuels such as monomethyl hydrazine hydrazine (hī`drəzēn'), chemical compound, formula NH2NH2, m.p. 1.4°C;, b.p. 113.5°C;, specific gravity 1.011 at 15°C;. It is very soluble in water and soluble in alcohol.  and nitrogen tetroxide te·trox·ide  
n.
A chemical compound containing four oxygen atoms per molecule.

Noun 1. tetroxide - an oxide containing four atoms of oxygen in the molecule
oxide - any compound of oxygen with another element or a radical
. This building was originally a hypergolic fuel manufacturing and loading facility. Constructed during the Cold War, the as-built drawings were sketchy at best. It appeared that many field mods were incorporated into the building without any corresponding changes to the drawings. Beginning at the top of slab elevation on the second floor, our thinking was that we could break the upper section loose and shove it off--we were wrong.

FINISHING TOUCHES finishing touches finish npl the finishing touches → der letzte Schliff

finishing touches nplultimi ritocchi mpl 
 

We discovered reinforcing bars at 8 inches on center, with two pieces of No. 11 rebar re·bar  
n.
1. A rod or bar used for reinforcement in concrete or asphalt pourings.

2. A group of such rods forming a grid.



[re(inforcing) bar.]
 [1.27-inch diameter] running in both directions. The walls were 12 inches thick, and the slab was 10 inches. When we finally broke this animal down, it was time to play with the footers. At 14 feet below grade, we found the footing bottoms and removed the last of the concrete. This monster took every bit of four weeks to drop and pull out of the ground.

[ILLUSTRATION OMITTED]

It is interesting to note that we encountered several miles of abandoned conduits, duct banks and pipes below this 60-year-old part of the facility.

All of the metals recovered from this project were responsibly recycled. In addition to the commodities, we recovered two double-walled stainless steel stainless steel: see steel.
stainless steel

Any of a family of alloy steels usually containing 10–30% chromium. The presence of chromium, together with low carbon content, gives remarkable resistance to corrosion and heat.
 hypergolic fuel storage tanks, which had never been used. Upon removal and inspection, we found that they had been completely shrouded in several layers of fiberglass, and connected to an active cathodic protection system, effectively preventing any corrosion.

Hangar "L" was used as a life sciences facility in support of the on-going Mars mission[s]. This hangar housed a series of plant growth chambers, operating theaters and dissection rooms. With its stated mission complete, the facility was mothballed and left to sit for several years.

Sunrise Systems employees constructed full negative pressure containments for the removal of thousands of square feet of asbestos-containing tiles, mastics insulation and wall/roof Transite panels.

We removed all PCB containing transformer oils, lighting ballasts and lead-based paints, and responsibly disposed of them. During abatement, we became suspicious of the cement panels used as a sub-roof base, and corrugated cor·ru·gate  
v. cor·ru·gat·ed, cor·ru·gat·ing, cor·ru·gates

v.tr.
To shape into folds or parallel and alternating ridges and grooves.

v.intr.
 panels along the outside of the high bay. Testing showed that these materials do in fact contain 25 percent to 28 percent chrysotile chrysotile: see serpentine.
chrysotile

Fibrous variety of the magnesium silicate mineral serpentine; it is the most important asbestos mineral. Individual fibres are white and silky, but the aggregate in veins is usually green or yellowish.
 asbestos. We are currently negotiating a substantial change order with the government to remove these materials prior to demolition of the structure.

While waiting for the change order, Frank-Lin Excavating moved in for the dismantling process. At the time of this writing, all work that can be completed on this facility has been finished, and we are waiting for word from our C.O. to start a large change order to remove an additional 28,000 square feet of asbestos containing Transite boards that were not identified in the pre-work survey.

The author is vice president of Sunrise Systems of Brevard Inc. and can be reached via e-mail at sunrisemark@cfl.rr.com.
COPYRIGHT 2007 G.I.E. Media, Inc.
No portion of this article can be reproduced without the express written permission from the copyright holder.
Copyright 2007, Gale Group. All rights reserved.

 Reader Opinion

Title:

Comment:



 

Article Details
Printer friendly Cite/link Email Feedback
Title Annotation:JOB STORY
Author:Ancona, Mark
Publication:Construction & Demolition Recycling
Date:Sep 1, 2007
Words:1065
Previous Article:Loading up: C&D recyclers and demolition contractors should consider machine size, operator comfort and service when choosing a loader.(EQUIPMENT...
Next Article:Worth the wait: a portable crushing plant helps Blessing Construction take control of its own concrete recycling.(COMPANY PROFILE)
Topics:



Related Articles
For Ian Anderson, the fire still burns.(Entertainment)(He's 60, but the leader of Jethro Tull still has the old passion for music)
A new look, a new adventure: you're holding the first complete issue of the new Advocate--an unveiling we've been working toward for many months...
Best care everywhere: here's an idea: a civilian VA for the uninsured, and maybe the rest of us.(SPECIAL HEALTH CARE ISSUE)
Dallas completes demo project.(C&D NEWS)
Precautionary measures: identifying exposures is the first step to managing environmental risk.(GREEN JOBSITE UPDATE)
Room to work: a crushing plant site supervisor spells out ground rules for productive work flow.(OPERATIONS FOCUS)
Loading up: C&D recyclers and demolition contractors should consider machine size, operator comfort and service when choosing a loader.(EQUIPMENT...
Worth the wait: a portable crushing plant helps Blessing Construction take control of its own concrete recycling.(COMPANY PROFILE)
Elevator, going down: Minnesota's Frattalone Cos. takes down a massive ConAgra grain elevator to make way for a football stadium.(JOB STORY)
Easy does it: dismantling using a crawler excavator is crucial to taking down a former Philip Morris manufacturing complex.(JOB STORY)

Terms of use | Copyright © 2009 Farlex, Inc. | Feedback | For webmasters | Submit articles